Home Contact Us Site Map

The Project
The Plans
Timeline
Old Timeline
Photos

 

Old Timeline
Early 2001
Start looking for a house.
Spring 2001
Still looking, we're not happy with anything we're finding. We've scaled up our price range significantly by this point, without notable success.
Late Spring 2001
We decide to build a custom home. We also start looking for land.
Early Summer 2001
We sign with Luxor for their design services. We continue looking for land.
Summer through early fall 2001
We meet several times with Luxor to discuss design. We're still looking for land.
Early fall 2001
We make an offer on a lot, but the restrictions, easements, and general difficulty of working with it eventually convince us to abandon the offer.
Late Fall 2001
We've seen several pieces of land that we liked, but none that were just right. We've decided on a basic concept and many of the details of the house we want to build, and feel we're closing in on a design. We put the development of the plans on hold temporarily until we find land, as the lot will, to a certain extent, dictate the final design of the house.
Early spring 2002
We see a lot that we like. We make an offer that's accepted.
Late spring 2002
Settlement on the lot, and we pick back up with the house design to finalize that.
Early fall 2002
We've pretty much finalized the design, so we sign the construction contract with Luxor and seek financing. It turns out that the lender we planned to use just flat-out doesn't loan this kind of money (go figure, they're one of the largest banks in the country), so we have to find an alternate source. At the same time, we start the process of obtaining the required permits. 
Late fall 2002
We get the septic and well permit applications back in the mail. They aren't approved, because the previous owner of the land, who had agreed to transfer his septic permit, did so by faxing a letter to the county. The county only accepts original signed documents. We think "The US government accepts faxes, so why not Chester County?" but know better than to argue with city hall.
Early 2003
We finally have the letter transferring the septic permit. (The previous owner didn't have much motivation to get this done in a timely fashion, since it wasn't costing him anything to delay. But it did get done.) All the paperwork gets dropped off with Luxor for resubmission. In the meantime, our construction plans have passed DEP review. This is required because of some wetlands at the edge of the property.
Late winter 2003
Hurray! We've got all the permits back except the building permit. We expect that momentarily.
March 15 2003
We take some photos to document the land before ground is broken, because we know the application for the building permit is in the hands of the county. 
Early April 2003
We have the building permit, or at least Luxor does. We expect to break ground very soon.